Adler TPP – most state-of-the-art power generating facility in Sochi – commissioned

RELEASE

Adler TPP

Infographics

gazprom_fin-en-preview.jpg

The Adler district of Sochi hosted today the celebrations dedicated to the commissioning of the Adler TPP.

Alexey Miller and Dmitry Medvedev at Adler TPP
Alexey Miller and Dmitry Medvedev at Adler TPP

Alexey Miller and Dmitry Medvedev at Adler TPP

The celebrations were attended by the Russian Government Chairman Dmitry Medvedev and the Gazprom Management Committee Chairman Alexey Miller.

Alexey Miller and Dmitry Medvedev at celebrations dedicated to Adler TPP commissioning
Alexey Miller and Dmitry Medvedev at celebrations dedicated to Adler TPP commissioning

Alexey Miller and Dmitry Medvedev at celebrations dedicated to Adler TPP commissioning

“At present, the Adler TPP is the most state-of-the-art and productive power generating facility in Sochi. A new energy heart of the city!

The commissioning of the brand-new thermal power plant enabled to significantly enhance power supplies to Sochi, secure uninterrupted electricity and heat supplies to sports and tourist infrastructure in the Imereti Lowland as well as to facilities intended for developing Sochi as a mountain resort. At the same time, the Sochi power district became considerably less dependent on the neighboring power networks – the Adler TPP output would cover over one-third of the projected peak demand at the time of the sports competitions in 2014. In the future, there are plans for the Adler TPP to provide heat supplies to the Blinovo residential district of Sochi.

Gazprom continues consistently reaching its strategic goal for the power sector – bringing its efficiency indicators to the level of the world's largest utility companies,” said Alexey Miller.

During the celebrations the Adler TPP power-generating units were brought to their full capacity of 360 MW.

Dmitry Medvedev and Alexey Miller with Adler TPP employees
Dmitry Medvedev and Alexey Miller with Adler TPP employees

Dmitry Medvedev and Alexey Miller with Adler TPP employees

Background

The Adler TPP is an advanced thermal power plant with the output of 360 MW (heat output – 227 Gcal/h) composed of two independent PGU-180 combined cycle gas turbine units. Each unit comprises two gas turbines manufactured by Ansaldo Energia (Italy) and a steam turbine manufactured by Kaluga Turbine Works.

In 2009 Gazprom Group launched construction activities at a site of 9.89 Ha. The project was implemented on the land with no infrastructure.

The configuration of the power station design and construction allows meeting all the main demands for power and heat generation as well as environmental requirements. Engineering solutions and materials applied during the Adler TPP construction are in line with the highest Russian and international environmental standards.

The main Adler TPP equipment is based on the advanced combined cycle gas turbine technology that secures high efficiency (52 per cent), low fuel consumption and an average 30 percent reduction of atmospheric emissions as compared with conventional steam turbines.

The Adler TPP cooling system is a closed-loop water supply system with dry ventilator cooling towers. Such a system does not lead to higher air humidity and environmental pollution due to cooled water circulating in a closed loop.

As the most eco-friendly energy source, natural gas is the main and backup fuel of the Adler TPP.

Owing to the state-of-the art engineering and architectural solutions, the station fits well into a unique natural landscape. Lawns and tree alleys are planted along the total area of 3 Ha occupying the Adler TPP premises. The first alley of ten deodars was planted in 2009 during the celebrations dedicated to the Adler TPP construction startup.

The Black Sea coast, including the city of Sochi, had traditionally been an energy dependent region. By the time the decision was made on the Adler TPP construction, local power stations were satisfying some 25 per cent of the city's power demand, the rest was supplied by power networks of the neighboring regions. Owing to the anticipated sharp increase in the energy demand in Sochi and in order to guarantee safe power and heat supplies to the sports and tourist infrastructure facilities in Sochi, the Adler TPP construction project was included into the Program for the Construction of Olympic Venues and the Development of Sochi as a Mountain Resort, approved by the Russian Government.

The Adler TPP is also the subject of OGK-2 contracts for power supply (OGK-2 is the Adler TPP operating organization. Gazprom Energoholding is the OGK-2 controlling shareholder).

Gazprom Investproject, a wholly-owned subsidiary of Gazprom acts as an investor. The Adler TPP construction project was the first independent project of Gazprom using the project financing principles. A loan from Vnesheconombank was taken for the project implementation purposes. As part of the Russian Regions Gasification Program and in order to ensure gas supplies to the Adler TPP, Gazprom Mezhregiongaz constructed a gas supply facility (within the Gas Pipeline to Adler TPP project) made up in two strings. The length of each string is 25.5 km.

 